Why Might Two Similar Data Centres Be Worth Very Different Amounts?

Two buildings with the same megawatts can be valued very differently, depending on their contracts, customers, power, connections and location.

The Physical World Behind AI, the Tech Innovations library

First published 30 October 2026 Last reviewed 29 October 2026 The Bigger Picture

Megawatts describe how big a data centre is, not what it is worth. A buyer values the income a site can produce and how secure that income is. A site full of customers on long contracts, with enough power to grow and many network connections, earns more and more reliably than an identical building that is empty or short of power. That is why two data centres of the same size can be valued very differently.

Valued on income

Digital Realty explains in its annual report that it values operating properties by an income approach, using either a discounted cash flow analysis or a capitalisation rate applied to a property's net operating income. It records separately the value of leases already in place, because having in-place tenants allows buyers to avoid the costs and lost rent of leasing up a property.

What moves the value

DriverWhy it mattersWhat owners report
Signed customers and contract lengthSecure, predictable incomeDigital Realty: larger deployments on contracts generally 5 to 10 or more years
Spread of customersLess dependence on any oneDigital Realty: more than 5,000 customers, none above about 11.5% of annualised recurring revenue at the end of 2024
PowerWithout it, space cannot be leasedEquinix: power, not space, is a limiting factor in many of its sites
Network connectionsCustomers pay to connect to each otherEquinix: diverse carrier fibre networks in its sites are critical
Location and timingScarce capacity commands better termsCBRE: primary North American market vacancy at a record low of 1.4% in the first half of 2026

Power as the scarce ingredient

Because new capacity depends on power, a site that already has it is worth more. JLL reports that the average wait for a grid connection in primary data centre markets exceeds four years, and CBRE reports that commitments had been made on 80.4% of all capacity being built in North America in the first half of 2026. Digital Realty also notes that growing interest from private investors has generally pushed capitalisation rates lower, which raises values for the same income.

What is not certain

  • Valuation depends on interest rates, investor appetite and the market at the time; none of the figures here are values of any particular site.
  • Company and broker figures describe their own portfolios and markets, mostly in the United States.

Sources and method

Method: each link was opened on 29 October 2026 and every figure was taken from the page or filing cited beside it, in the currency stated there; shares marked as calculated are simple arithmetic on the cited figures. Company and consultancy figures describe their own data and models; they are not recommendations.