Power and Energy

Even When the Money Is Ready, Why Is the Power Not?

A data centre can be built in a couple of years, but new grid lines, transformers and connections often take longer, and that has become the pace-setter for AI.

The Physical World Behind AI, the Tech Innovations library

First published 30 October 2026 Last reviewed 29 October 2026 The Bigger Picture

A large data centre needs a large, reliable connection to the electricity grid. Building the halls is the quick part. The connection may need new transmission lines, new substations and new power stations, and each of those has to be studied, approved, supplied and built. Around the world, these steps now take longer than building the data centre itself. That is why access to power, rather than money or land, often sets the pace for new AI capacity.

Queues to connect

In the United States, Lawrence Berkeley National Laboratory counted about 10,300 projects actively seeking grid interconnection at the end of 2024, representing 1,400 GW of generation plus about 890 GW of storage. It found that the median time from a connection request to commercial operation has doubled, from under two years for projects built in 2000 to 2007 to over four years for those built in 2018 to 2024, and that only 13% of the capacity that asked to connect between 2000 and 2019 had reached commercial operation.

Years to build the wires

The International Energy Agency reports that new grid infrastructure often takes five to 15 years to plan, permit and complete. Equipment is a bottleneck too: it now takes two to three years to procure cables and up to four years to secure large power transformers, and waits for direct current cables extend beyond five years. In one example from Korea, a 345 kV line took 22 years to build, mainly because of local opposition.

StepTypical time citedSource
Connection request to operation, US projects built 2018 to 2024Over 4 years (median)Lawrence Berkeley National Laboratory
Plan, permit and complete new grid infrastructure5 to 15 yearsInternational Energy Agency
Procure cables2 to 3 yearsInternational Energy Agency
Secure large power transformersUp to 4 yearsInternational Energy Agency

What it means for AI

The IEA notes that in its highest-growth scenario, long grid connection queues mean that much of the extra electricity for data centres would be met by fossil fuels, simply because those plants can be connected sooner. Operators respond by choosing sites near existing capacity, planning connections years ahead, adding on-site power and storage, and offering to be flexible so that they can connect sooner.

What is not certain

  • Connection times differ greatly by country, region and grid operator; the figures here come mostly from the United States and global averages.
  • Queues include many projects that will never be built, so their size overstates real demand.
  • Supply chains for cables and transformers may ease or tighten as factories expand.

Sources and method

Method: each link was opened on 29 October 2026 and every figure was taken from the page cited beside it. No figure was estimated.

Read next

This article provides general information, not investment advice or an offer of securities.